Bond Updates and Information

Proposition A

New Elementary School

  • Named Huckabee as Architect of New Elementary Campus and Prop B multipurpose center
    (Huckabee fee is 5% of project cost)

  • REEDER Construction selected as the Construction Manager at Risk
    (Construction service fee at 1.25%)

  • Elementary School construction budget $46 million. Some of this money has been invested through First Financial and Logic.

  • Blueprints are 100 % Completed.

  • Construction began on time.

  • Groundbreaking Ceremony Monday, April 22nd.

Safety & Security

  • Ongoing updates across the district including:
    Adding and updating existing cameras
    Securing doors across the district
    Fencing

  • Safety and security budget across district - $275,000 allotted through bond, in addition to state grants currently awarded and pending. Total current budget is slightly over $1 million.

Land to Accommodate Growth

  • Purchased 20 acres located at 1189 and Pritchard Lane for $1,300,000

  • Quarterly reports submitted to BISD from ONEOK show monitored readings of three wells in the southeastern most corner of the future school site. Readings monitor groundwater composition and have declining negligible measurements each quarter. No limitations on construction or habitation, beyond restriction on well water use. School site will use Parker County Special Utilities District Co-Op water, not groundwater.

  • Terracon - Soil composition reports clear and site ready for construction. Potential Vertical Movement (PVM) only 1 inch

    Buses

  • Have ordered 5 buses for a combined $847,219

  • All buses have enhanced safety features, heat, and AC

Wastewater Treatment Plant

  • Intermediate and Junior High plant is in the design phase

  • Researching the possibility of utilizing the existing plant at the elementary and high school for the new elementary.

  • Wastewater Treatment Plant repair & install are estimated at $1.7 million. There
    is a potential money-saving option by tying the new elementary campus in with the high school wastewater plant.

Proposition B

Multipurpose Student Center

  • Approved Huckabee as architect at 5.5 percent.

  • Will name CMaR on May 13, 2024.

Proposition C

Safety at Stadium

  • Paragon successfully replaced new synthetic turf for $830,534 total cost
    $700,000 of this project was funded by the 2023 Bond

  • The District acquired tools to assist in routinely maintaining the field and Paragon will maintenance the field annualy

Complete!

Brock Community Committee

The Brock Community Committee is made up of Brock citizens to ensure the District is meeting community goals and expectations

Members

Kristin Arredondo
Earl Bilbrey
John Brunner
Todd Carpenter
Elaine Dieball
Cody Lane
Shayna Yancey

View Meeting Minutes:
December 2023


Bond Community Committee Introduction Video